Main Campus/Emergency Department: Construction Blog
Intelligent Medicine By Design
04/04/2011
Keep an eye out for our new ads that are now appearing in local newspapers.
Topping off the MOB
03/25/2011
The final steel beam is now place on the medical office building on the west side of the New Main Campus.
The final stretch
03/17/2011
Today marks 100 days until the opening of the new EMH.
Construction is nearing an end
02/24/2011
We recently received our temporary certificate of occupancy for the New Elmhurst Memorial Hospital, signifying that the construction process is coming to an end.
The idea behind "onstage and offstage"
02/03/2011
The layout of the new Hospital is designed for maximum efficiency, using a common-sense approach that we call "onstage and offstage."
Inpatient units with a neighborhood feel
01/21/2011
All of our inpatient suites will be grouped into 12-bed "neighborhoods" that keep caregivers close to their patients and the supplies and equipment they need.
A private room in the Emergency Department?
01/13/2011
We're replacing the conventional curtain-separated bays with individual rooms, each with its own restroom and an adjacent family waiting area.
Not just private rooms...identical private rooms
12/22/2010
The new EMH will include all private inpatient suites. Beyond that, they will all be the same, instead of mirro images of each other, which increases safety and efficiency.
200 days and counting
12/07/2010
June 25, 2011 - the opening date for the new Elmhurst Memorial Hospital - is just 200 days away.
Construction begins on medical office building
12/03/2010
Construction begins on medical office building located on the west side of the Elmhurst Memorial Hospital New Main Campus.